Electrodes for Earthing or Grounding System in Building Construction

A. Ground Rod:

16 mm diameter stainless steel. Driving head is to be high strength steel. Couplings are to be long length silicon bronze, internally threaded. Threads are to be rolled onto rod to ensure uniform layers of copper and strength. Earth rod is to be complete with non-corrosive couplings, head and bolted connector of sufficient size, and number of bolted clamps to connect all cables terminated thereto.

Low Voltage (LV) Power Cables In Electrical Construction Works

The scope of work shall cover laying, connecting, testing and commissioning of low voltage power cables complete with all cable support, cable, cable trays, clamps and joints. Cables to be purchased from who regularly engaged in the manufacturer of electrical cable and wire products of the types and ratings required, whose products have been in satisfactory use in similar service not less than 5 years. The standard of the cables shall comply with National Electrical Manufacturers Association of local standards or any other approved.

Guidelines for Installation of Emergency Power Diesel Generating Set

We often depends Diesel Electrical Genset as emergency power system due to mains failure. As a professional, the installation of diesel electrical power generator should be as per the clients requirement and to be inline with the authoritative norms and standards. Safety, security, convenience, future expansions etc are to be considered and co-ordinated before start detailing of the genset's installation. The generator should be as close to the main change-over board as possible. In cases like Textile Mills, where there is fear of smoke affecting the quality of the yarn etc., generators may be located away from the Plant / Department.

Automatic Transfer Switch (ATS) OR Automatic Mains Failure (AMF) Panel

Reliable electrical power becomes one of the most wanted factor in modern world industry where operation should be uninterruptible and maximize the cycle of operation, output quality and to avoid losses and damages. Here we are talking about Automatic Transfer Switches (ATS) also known as Automatic Mains Failure (AMF) panel to cater uninterrupted power supply from Mains or backup sources like Diesel gen-set, static ups etc.

What is Automatic Transfer Switch (ATS)?

Automatic Transfer Switch (ATS) is an automated switching device that transfers load power to backup power during mains failure and back to its original state when mains power reinstate to the normal condition. It will have its own contacts, microprocessor to analyses the conditions whether power supply is normal or backup and need backup or mains power. Here "back up power" may become either Standby generator or another mains power or static power source like UPS.

 

Lighting Distribution Boards (LDB) In Electrical Construction Works

Lighting Distribution Boards (LDB) are an integral and essential part of every building project and it must be designed, manufactured and installed all in accordance with the safety standards. In most of the cases it operates a layman wherein others operate dedicated or trained person. This article explains what are the essential standards, parts, frame to be applied for manufacturing and installation of lighting distribution boards in a quality building project.

Electrical Earthing or Grounding Electrode Design for Building Construction

Earthing or Grounding Electrode for an effective and reliable electrical earthing system requires proper survey and analysis of project location, type of structures installed and electrical / electronic equipment used in the entire system. The design calculation of the earth electrode systems shall be based on the approved earth resistivity data and the system's fault currents and their duration.

Capacitor Banks in Electrical Construction Works

Capacitor banks help to improve the quality of the electrical power and gives us the more efficient operation of the power system. Capacitor banks are inexpensive if we compare the benefits they deliver to overall power system and can be easily installed anywhere on the network. Automatic Power-factor Correction (APFC) Capacitor Banks also known as Shunt Capacitor Banks (SCB) are installed to provide reactive compensation and power factor correction. The use of APFC improve voltage regulation, saves power loss and improve transmission capabilities.

Installation of Structured Cabling For Voice / Data System In Building Construction

The Contractor shall design, supply and install outlet plates, conduits, trunking, trays, wiring, junction boxes, distribution frames, patch panels, data rack, backbone cables, etc. necessary to form a complete structured system for voice and data cabling within the buildings. Cabling / wiring shall be provided for voice system from patch panel location to each voice/data outlet. Draw wires shall be provided in conduits for future data cabling / wiring by others (if applicable). The installation shall comply with the requirements of ANSI / EIA / TIA-568-1991 as appropriate as well as Local Telecom Authority.

Voice and data outlet plates shall be designed to accept industry standard RJ45 plugs.

Electrical Grounding or Earthing Conductors in Building Construction

Buried Earth Conductors:

PVC insulated copper strip conductors or PVC insulated stranded copper cables with cross-section min 70 mm2 or as per earthing calculation.

Earthing Conductors:

PVC insulated copper conductor as described in the Specification for the particular application.

Indoor MV Distribution Panel Boards In Electrical Construction Works

Building projects requires MV Distribution Panel Boards for distribution of power to each utilities. A good electrical distribution network will have proper design, right components, and future load provisions. Space utilization will also be an important factor for maintenance and handling of the equipment. Here we look into what are the features required for design, manufacture, install a MV Distribution panel board including its BIS (IS) standards that serving quality building projects.

Medium Voltage Cables (MV Cables) In Electrical Construction

The contractor shall supply, install, test and commission the 13.8 KV cable network as shown and indicated on the contract documents. Conductor sizes shall be metric as shown, conductor sizes with cross sectional areas smaller than specified will not be accepted. The cable installation shall include all trench work, sleeves, ducts, and all necessary fixings and cable terminations at both ends of the cable. The contractor shall supply and install cable marker posts to indicate the route of all underground cables. Markers shall be provided at every bend along the route and at sites of crossing roads or pipe lines.

Value Engineering and Its Importance In Engineering Industry

The value is a function of cost. Therefore, it can be increased either by improving the function or reducing cost. The maximum value is achieved when the function performs reliably at the lowest cost. A key principle of value engineering that basic functions be preserved and not reduced as a result of improvements in value. Thus Value Engineering (VE) is a systematic method to improve the "value" of goods, products or services through an examination of the function.

Methods of Installing External, Exterior and Outdoor Lighting System

Installation Methods of External, Exterior and Outdoor Lighting System includes lighting equipment luminaires, control gears, panel boards, poles, brackets, cabling, and allied minor civil works. All installations are to be carried out under strict supervision of qualified supervisors and engineers. If installation required heavy vehicles, extreme care has to be taken for preventing damages of lighting equipment, control gears and poles.

Method of Electrical Earthing And Bonding Multicore Cables

The metallic sheath and armour of multicore cables shall be bonded together and earthed.

Cable earthing conductors shall be copper strip with appropriate section laid in formed cable trenches or ducts, or fixed to walls, concrete or steel work, by means of clamps or claw type cleats, appropriately secured into suitable wall plugs or tapped holes. The spacing of fixings shall not be greater than 1 m. Where earth strip is buried or laid in positions in which there is danger of corrosion it shall be provided with a corrosion-proof serving of extruded thermo-plastic or self-adhesive PVC tape which for short lengths may be hand applied on Site.

Typical Installation Details and Drawings

Construction projects highly depends on typical installation details and drawings. Architects and engineers use this kind of information to reduce their work load. Employees particularly technicians and foremen who execute the project uses typical drawings as general guidelines where repeated structure, forms, shapes, operations, loads, etc. come into force.

Vacuum Interrupter (VI) for Vacuum Circuit Breakers (VCB)

Vacuum Interrupter (VI) are vacuum sealed-off devices incorporated in Vacuum Circuit Breakers (VCB) to cause interruption of fault currents in medium voltage electrical distribution systems. The contacts of the VI are pressed against each other under normal circuit conditions. In the event of a fault current, the VCB mechanism effects withdrawal of the movable contact from the fixed contact.