Method of Earthing or Grounding Of MDB, Panel Boards, Lighting And Wiring Installations

Method of Earthing To Main Distribution Board (MDB)

Main earthing bar is to be provided in main distribution room and connected to earth electrode by 2 insulated conductors (minimum 150 mm2) via testing joints. Earthing bars of main distribution boards are to be connected, by insulated earthing conductor, directly to main earthing bar at main distribution room.

High Voltage and Low Voltage Power Cables In Electrical Construction

This article explains electrical power cables used in construction works complete with supply, installation, testing and commissioning of High Voltage (HV) and Low Voltage (LV) cables. All cables shall conform to standards of IS 7098-1973, IS 1554-1976 and wiring cables to IS 694-1977 however, contractor shall comply with the latest or superseded versions of IS/BIS to be used for the complete work.

Conditions Of Sub-Contract Agreement In Construction

Occasionally Main Contractor of the construction work depends sub-contractor for accomplishing some smaller or part of the project that may require specialized technical know-how and installation methods. In those cases Main contractor selects some sub-contractors who has capacity to achieve the task within the given time frame. Hence both of the parties, ie., Main contractor and Sub-contractor to be signed an agreement which protects both the parties' interest. Here is a sample for Conditions of Sub-contract Agreement in Construction Works.

Execution Method of Electrical Earthing or Grounding Installation

Continuity: Ensure that complete earthing system is electrically continuous and mechanically secure. Locations of main earth bars in substations, electrical rooms, mechanical rooms, hub (Technical) rooms, etc., to be clearly identified by 100mm X 100mm white traffolyte labels, with red lettering, to Engineer's approval.

Construction Specification For Electrical Busbar Trunking (Bus Duct) System

Busbar Trunking System (BBT) in electrical construction, uses to transporting electrical power to a shorter distance but many utilization point, say, within the building or a compound of facilities. Though cables can also be used in these areas, their economic impact would be high if compared to the effective Busbar Trunking System. It will help us to tap power directly from where we want it to be and make utilize to the service point.

Transformers in MV Distribution System

This specification intended to supply, install, test and commission mineral oil immersed 1500 KVA, 3 phase indoor transformers, fitted with cable boxes, bolts, and all necessary accessories. Transformers shall be indoor type, oil filled, two winding, four off load capacity, 2.5% taps, two above and two below high voltage rating in compliance with IEC 76 or BS 171.

Electrical Engineering

Electrical engineering deals with practical applications involving current flow through conductors; focuses on the design, construction, and operation of electrical systems and equipment. It includes developing, producing and testing of electrical and electronic devices and equipment, such as, generators to produce and distribute electricity, electric motors and other electrical machinery, transmission line.

Fire Alarm System In Electrical Construction Works

Fire Alarm System installation work covered by this section of the specifications includes the furnishing of all labor, equipment, materials, and performance of all operations in connection with the whole Fire Alarm System as shown on the drawings and as herein specified. The requirements of the conditions of the Contract, Supplementary Conditions and General Requirements apply to the work specified in this section.

Method of Electrical Earthing And Bonding Multicore Cables

The metallic sheath and armour of multicore cables shall be bonded together and earthed.

Cable earthing conductors shall be copper strip with appropriate section laid in formed cable trenches or ducts, or fixed to walls, concrete or steel work, by means of clamps or claw type cleats, appropriately secured into suitable wall plugs or tapped holes. The spacing of fixings shall not be greater than 1 m. Where earth strip is buried or laid in positions in which there is danger of corrosion it shall be provided with a corrosion-proof serving of extruded thermo-plastic or self-adhesive PVC tape which for short lengths may be hand applied on Site.

Guidelines for Installation of Emergency Power Diesel Generating Set

We often depends Diesel Electrical Genset as emergency power system due to mains failure. As a professional, the installation of diesel electrical power generator should be as per the clients requirement and to be inline with the authoritative norms and standards. Safety, security, convenience, future expansions etc are to be considered and co-ordinated before start detailing of the genset's installation. The generator should be as close to the main change-over board as possible. In cases like Textile Mills, where there is fear of smoke affecting the quality of the yarn etc., generators may be located away from the Plant / Department.

Quality Plan for Construction Projects

It is essential that services and systems in a building construction contract work are provided to conform to the requirements of the customer, and that the activities be effected as economically as practical. The achievement of these objectives is facilitated by setting up working procedures and practices, which collectively provide a “Work Efficient”, yet controlled operating environment. It is the purpose of this Construction Quality Plan to give instruction to personnel, on the implementation of the company system such that the above objectives are accomplished. Documentation specific to the project will be provided to ensure full compliance with the particular requirements of the contract.

Low Voltage (LV) Switchgears in Electrical Construction Works

Low Voltage Switchgear are familiar to every people since they are the controlling mediators between low voltage utilities and equipment with human beings. Be it a common home DB or an isolator or control centres, they all are being manufactured to use untrained people ie., common people. The scope of works shall cover the supply installation, testing and commissioning of main and sub-distribution boards, panel boards, fusible safety switches, circuit breakers etc. Associated minor building works require for the erection of the distribution boards and panels shall be included in the scope of work.

Typical Installation Details and Drawings

Construction projects highly depends on typical installation details and drawings. Architects and engineers use this kind of information to reduce their work load. Employees particularly technicians and foremen who execute the project uses typical drawings as general guidelines where repeated structure, forms, shapes, operations, loads, etc. come into force.

Vacuum Interrupter (VI) for Vacuum Circuit Breakers (VCB)

Vacuum Interrupter (VI) are vacuum sealed-off devices incorporated in Vacuum Circuit Breakers (VCB) to cause interruption of fault currents in medium voltage electrical distribution systems. The contacts of the VI are pressed against each other under normal circuit conditions. In the event of a fault current, the VCB mechanism effects withdrawal of the movable contact from the fixed contact.

Method of Lightning Protection System For Building

Comply with the General Conditions, Supplementary Conditions and the requirements in various Sections of the Electrical Specification. In addition read and conform to all Electrical Sections of these specifications. The installation shall comprise air networks connected to roof and down conductors and finally terminated in earth electrodes, via structural re-bars and suitable test points in accordance with the details included on the attached drawings or in the Specification Section.

Earthing or Grounding Method For Transformer Substation

MV switchgear and MV cables are to have separate main earthing bar connected to framework or earth bar of each item by insulated conductor and the earth-electrode by 2 insulated earthing conductors, one at each end of bar, via testing joints. Earthing conductor is to be minimum 150 mm2.

Payment Application Format For Construction Companies

Construction companies normally submit Payment application every month as per the contract agreement. Until completion of the project, they get part payment from their client after submission of claim which is duly approved and certified by project consultant. Project QS collect all the relevant work details and progress percentage from the field engineers in close coordination with Project Manager.