Hoisting Facilities in Construction Site Logistics

The Hoisting and Craneage Plan shall include a layout for all hoist/crane infrastructures. The Plot Developer should consider all detailed information such as hoist arrangements, platforms, loading deck, mast sections, hoist equipment, details of attachment to building, gates, fences, safety devices, overload protection, etc.

Hoisting Facilities in Site Logistics

The developer must ensure that all hoists/cranes will not interfere with hoists/cranes and construction activities on adjacent plots. Proof of coordination with adjacent plot developer shall be submitted to the master developer.

The Plot Developer is responsible for all associated testing, permits for hoisting and craneage operations as may be required by the local authorities. The Plot Developer should employ only those hoisting and craneage operators approved by Local Authority.